We're darn close and the P3 is proceeding on plan so far. Everything has
been released to production and we are just awaiting delivery of the
final production sheet metal and stuffed PCBs. We're also refining the
firmware as we go through field test over the next couple of weeks.
Based on where we were a week ago, my best estimate is somewhere between
7/15 and 7/25 for initial shipments. It will then take about 4-5 weeks
to ship all of the rather large backlog.
73, Eric WA6HHQ
_..._
On 7/3/2010 6:42 PM, Don Cunningham wrote:
> Can someone at Elecraft comment on the shipment of the first P3's?? Are we truly just under two weeks for the first ones, or has a setback occurred?? Inquiring minds with orders in place would like to know.
> Thanks for all you do,
> Don, WB5HAK
>
>
______________________________________________________________
Elecraft mailing list
Home:
http://mailman.qth.net/mailman/listinfo/elecraftHelp:
http://mailman.qth.net/mmfaq.htmPost: mailto:
[hidden email]
This list hosted by:
http://www.qsl.netPlease help support this email list:
http://www.qsl.net/donate.html